The Trees on Septic Site are Cleared
(Trees arked, Felled and Removed)
March 7th, 2008
Wiring of Electrical System Continues
(Power Outlets, Lights and Conduits)
February 29th, 2008
Wiring the A/V and Computer Systems
(Wiring Installed for Audio, Visual and Computers)
February 1st, 2008
Work Continues of Building's Exterior
(Exterior Trim and Entry Ways constructed)
January 18th, 2008
Wiring of Electrical System Begins
(Power Outlets, Lights and Conduits)
December 21st, 2007
Weather Proofing of the Kitchen Roof
(Boarding, taring and shingling of the roof)
November 9th, 2007
Fixing in Place of Kitchen Roof Struts
(Moving, Placing, and Fixing in Place of Roof Struts)
October 26th, 2007
Siding, Trimming, Decking and Roof
(Work continued on Siding, Trimming, Deck
Glazing, Decking and Siding
(Installation of Doors, Decks and Siding on Upper Level)
August 10th, 2007
Siding and Miscellaneous Work
(Roofing, Siding, Glazing, Electrical and Plumbing)
July 13th, 2007
Work will continue on Roof
(Moving, Placing, and Fixing in Place of Roof Struts)
June 29th, 2007
Fixing in Place of Roof Struts
(Moving, Placing, and Fixing in Place of Roof Struts)
June 15th, 2007
Framing of Mezzanine Level
(Construction of support frame and exterior walls)
June 1st, 2007
Work Began on Dining Room Roof
(Framing of the roof and laying of Mezzanine Footers)
May 25th, 2007
Framing of the Upper Level
(Framing of the Interior / Exterior Walls Continued)
April 20th, 2007
Framing of the Upper Level
(Framing of the Interior / Exterior Walls Begun)
April 6th, 2007
Floor of Main Level Laid
(Main floor installed, plus additional framing)
March 23rd, 2007
Structural I-Beams Installed
(Supporting I-Beam for main floor installed)
February 16th, 2007
Framing of the Basement Walls
(Basement Walls Framed in)
January 26th, 2007
Basement Floor Poured
(Installation of under floor heating, concrete poured)
December 15th, 2006
Backfilling / Leveling
(Backfilling of site and leveling of floor)
November 26th, 2006
Basement Walls Poured
(Forms built, rebar set,concrete poured )
October 20th, 2006
Foundation Laid
(Forms built, concrete poured, rebar set)
October 6th, 2006
Excavation Complete
(Digging, Leveling and Preparing)
September 29th, 2006
Preparing the Ground
(Cutting, Blasting, and Digging)
September 22nd, 2006
Breaking Ground
(Celebration and Dedication)
August 15th, 2006
The Decision to Build
(The Need, Prayer, and Decision)
March 21st, 2006